date not in the factory calendar (future). When updating start date or finish date of project, system returns error co 500 or co 501. How to fix this error?

date not in the factory calendar (future) While i am trying to look at gantt chart from cj20n an information message shows up date not in the factory calendar (future). Enter a date which lies withing the validity period of the factory calendar. But i have not maintained the factory calendar in the.












Error Message Extract From Sap System.
When updating start date or finish date of project, system returns error co 500 or co 501. Enter a date which lies within the validity period of the factory calendar. Enter a date which lies withing the validity period of the factory calendar.
The 'To Date' Of An Interval Of Available Capacity Must Be Maintained So That It Is Within.
Then use t.code scal, select the factory calendar and click. What you can do is set the factory calendar used by the plant (seen in ox10) to be valid until 3759. Check the calendar assigned to the plant you have created in t.code ox10.
While I Am Trying To Look At Gantt Chart From Cj20N An Information Message Shows Up Date Not In The Factory Calendar (Future).
When creating/changing date of network activity,. This can be done in transaction oy05. How to fix this error?
But I Have Not Maintained The Factory Calendar In The.
The factory calendar settings have been transported from quality to production system the following warning message is raised: